Memorial Pavilion – Building progress
Week 8. 14th – 18th Apr
14th Apr 2014
The entrance lobby steelworks has been completed ready for the block walls to be built around it
14th Apr 2014
Blocks being laid around the completed steelworks
14th Apr 2014
The blocks around the steelworks have been completed awaiting the holes to be filled with hardcore to be ready for the first layer of the concrete floor
15th Apr 2014
The blockwork around the rooms has been completed to then be filled with hardcore ready for the first layer of the concrete floor. The rooms you see now (left to right) are the main entrance lobby, kitchen, store room and the main hall. The photograph is taken from the meeting room
15th Apr 2014
The drain pipes in the kitchen have been installed. The drain in the middle is the floor cleaning drain with the sink drain near the far wall
15th Apr 2014
The main hall roof posts have been back filled with concrete to assist in supporting the post and the roof
15th Apr 2014
This shows the two posts inserted into the South wall as protection for the wall in a really strong wind
16th Apr 2014
The main hall has had the holes around the posts concreted in, hardcore placed and compacted and sand laid over the hardcore floor in preparation for the reinforcing to be laid ready for the concrete
16th Apr 2014
Changing room 2 has had the waterproofing membrane put down and the reinforcing is being fitted ready for the concrete to be laid
16th Apr 2014
The lobby blockwork has been completed and is being filled in to be ready for the concrete floor to be laid
17th Apr 2014
The reinforcing steelworks has been placed in the Meeting room and Main Hall floor ready for the concrete to be laid
17th Apr 2014
The reinforcing steelworks has been placed in the Referees changing room, disabled toilet, lobby, kitchen and store room floor ready for the concrete to be laid
17th Apr 2014
The reinforcing steelworks has been placed in the canopy floor ready for the concrete to be laid. The concrete foundations for the steps have also been laid ready for the steps to be constructed. Hardcore has been laid in the disabled access slope behind the canopy area