Memorial Pavilion – Building progress
Week 6. 31st Mar – 4th Apr
31st Mar 2014
The car park area is having the second layer of hardcore laid down on top of ground cloth and plastic netting
31st Mar 2014
The West wall brickwork is now above the plinth brick line and the middle section is being made ready for the flint-work
31st Mar 2014
The West wall North corner is beginning to have its block work laid down
1st Apr 2014
The West wall North corner has progressed to the brickwork stage almost to the plinth brick-line
1st Apr 2014
Flints are now being mortared in. Note the vents for the shower rooms
1st Apr 2014
Hardcore has been laid into the trench ready for the concrete to be poured to lay down the kerbstones
2nd Apr 2014
The kerbstones have now been laid down in preparation for the top fill of hardcore on the car park area
2nd Apr 2014
The West wall North corner brickwork has now reached above the plinth brick-line
3rd Apr 2014
Hardcore to be laid down on protective ground cloth and plastic netting
3rd Apr 2014
Smaller graded hardcore been laid and compacted down
3rd Apr 2014
Further progress on the West wall
3rd Apr 2014
Smaller graded hardcore has been laid and compacted down over most of the car park area
3rd Apr 2014
Further progress on the West wall North corner