Memorial Pavilion – Building progress
Week 5. 24th – 28th Mar
24th Mar 2014
The rainwater drains have been installed along the North wall
24th Mar 2014
The rainwater drains have been installed along the South wall
24th Mar 2014
The rainwater drains have been installed along the West wall. All these drains will take rainwater into the two collection tanks installed for irrigation of the bowls and tennis lawns
24th Mar 2014
Reinforcing has been installed in the blockwork to help prevent wall movement in the event of a 100 year flood
25th Mar 2014
The sewer drains have been installed along the North wall and are connected to the main sewer pipe installed under the river
25th Mar 2014
The power cable pipe trench being dug
25th Mar 2014
The power cable pipe has been installed in the trench ready to be extended across the playing field to be able to connect the mains cable to the power pole on Leicester Road
25th Mar 2014
The rainwater drains are being installed along the East wall into the soak-away
26th Mar 2014
The trench being dug out to put in the water pipe and the telephone cable pipe to the building
26th Mar 2014
West wall blocks being built up on the North corner
26th Mar 2014
West wall blocks being built up on the South corner
26th Mar 2014
West wall blocks being built
27th Mar 2014
Digging out the car park ready for the car park kerb stones to be laid
27th Mar 2014
The area of stones shows the position of the soak-away that drains the East wall area of rainwater
27th Mar 2014
Mains water pipe (blue), electric cable access pipe (black) and the pipe for the telephone cable connection (grey) are all in place ready for the walls to be built
27th Mar 2014
The internal blocks are being erected on the West wall with insulation being installed as the wall is built. The two gaps are for the changing room doors out onto the car park
28th Mar 2014
Trench dug and marked out for the kerbing stones between the grass and the hardcore surface of the car park
28th Mar 2014
The kerbing stones will go around the whole car park area
28th Mar 2014
The plinth wall has started to be laid on the West wall and the insulation installed
28th Mar 2014
This shows progress on the West wall. The two round orange pipes in the wall are for the fresh air ventilation into the changing rooms