Memorial Pavilion – Building progress
Week 40. 24th – 28th Nov 2014
24th Nov 2014
The door has been fitted on the shower room in Changing room 1
24th Nov 2014
The door has been fitted on the shower room in Changing room 2
24th Nov 2014
The children’s play area fence from the play area
24th Nov 2014
The children’s play area fence from the play area
24th Nov 2014
The entrance mats have been installed in the mat wells, this is the one in the corridor
27th Nov 2014
The kitchen is now complete and ready to use on the 29th Nov. The splash-backs will need to be installed later
27th Nov 2014
The oak bridge fences have now been completed
27th Nov 2014
The chairs and tables for the Main Hall and the Meeting room have arrived
27th Nov 2014
The tables for the Changing rooms have arrived, the chairs arrived earlier
27th Nov 2014
The tables and the large window blind in the Main Hall
28th Nov 2014
10 of the volunteers are busy preparing the kitchen for the Christmas Fayre the next day
28th Nov 2014
This is the aspect from the road of the east wall