Memorial Pavilion -Building progress
Week 4. 17th – 21st Mar
18th Mar 2014
Meeting room with the hardcore laid in ready for the first lay of the concrete floor
18th Mar 2014
The disabled toilet and Ref’s shower room drains in place
18th Mar 2014
West wall with main drains in place. The slopping wall section in the middle is to allow for the slope in the floor for the shower rooms drains
18th Mar 2014
Shower rooms, changing rooms and toilets drains in place ready for the first level of floor concrete
19th Mar 2014
Changing room 1 showing the compacted hardcore ready for the first pour of floor concrete
19th Mar 2014
Meeting room showing the compacted hardcore almost ready for the floor concrete
19th Mar 2014
Changing room 2 showing the hardcore being compacted to be almost ready for the floor concrete. The toilets and showers area has also been compacted
20th Mar 2014
Changing room 1 damp proofing and reinforcing prior to the first layer of concrete on the floor
20th Mar 2014
Protecting wall erected along the bowls green edge ready for the drains to be installed and hardcore laid down
21st Mar 2014
South side rainwater drains laid down ready for the hardcore for the bowls green pathway to be filled in
21st Mar 2014
The first delivery of concrete was put in the toilets and shower rooms floor
21st Mar 2014
Second delivery of concrete being laid in the changing room 1 floor.
21st Mar 2014
Both the changing room 1 and the toilets and shower rooms floor slabs laid and smoothed over