Memorial Pavilion – Building progress
Week 37. 3rd – 7th Nov 2014
3rd Nov 2014
The kitchen cabinets are beginning to be installed
3rd Nov 2014
The kitchen cabinets are beginning to be installed
3rd Nov 2014
The sink is being installed in Changing room 2
3rd Nov 2014
The vinyl flooring has been laid in the Gents toilet
3rd Nov 2014
The galvanized fence and gate has been installed on the East end of the South side path
3rd Nov 2014
The galvanized fence and gate has been installed on the West end of the South side path
4th Nov 2014
The vinyl flooring has been laid in the store room
4th Nov 2014
The cubicle panels have been erected in the Gents toilet
4th Nov 2014
The kitchen base cabinets have all been installed on the supporting metal frames so allowing cleaning of the floor under the cabinets. The extractor hood for the cooker has been fitted
5th Nov 2014
The sink install in Changing room 2 nears completion
5th Nov 2014
The toilet cubicles have been installed in the Ladies toilet
5th Nov 2014
The toilet cubicles have been installed in the Ladies toilet
5th Nov 2014
The washbasins install in the Ladies toilet has been completed
5th Nov 2014
The first coat of the upper wall colour has been applied in the Main hall
5th Nov 2014
The first coat of the upper wall colour has been applied in the Main hall
5th Nov 2014
The fittings have been installed in the Disabled toilet
6th Nov 2014
The sink install in the Refs room is now complete
6th Nov 2014
The first Bridge fence rails have been fitted to the posts
6th Nov 2014
The first Bridge fence rails have been fitted to the posts
6th Nov 2014
The second handrail has been fitted onto the wall for the disabled access ramp