Memorial Pavilion – Building progress
Week 36. 27th – 31st Oct 2014
27th Oct 2014
The Kitchen has had its vinyl flooring laid
27th Oct 2014
The Kitchen has had its vinyl flooring laid
27th Oct 2014
The shower room in Changing room 2 has had its vinyl flooring laid
27th Oct 2014
The Refs room has had its vinyl flooring laid
28th Oct 2014
Changing room 1 has had its vinyl flooring laid
28th Oct 2014
Changing room 1 has had its vinyl flooring laid
28th Oct 2014
Changing room 2 has had its vinyl flooring laid
28th Oct 2014
The metal frames shown in this photo are the cabinet support frames that will allow the floor area under the cabinets to be cleaned easily. The gap is where the fridge will be
29th Oct 2014
The metal frames shown in this photo are the cabinet support frames that will allow the floor area under the cabinets to be cleaned easily. The gap is where the cooker will be
29th Oct 2014
The chosen colour has been painted on the Ladies toilet walls
29th Oct 2014
The chosen colour has been painted on the Gents toilet walls
30th Oct 2014
The chosen colour has been painted on the Lobby walls
30th Oct 2014
The Whiterock waterproof plastic wall covering is being put up on the Shower room 1 walls
31st Oct 2014
The Whiterock waterproof plastic wall covering has been put up on the Refs Shower room walls
31st Oct 2014
The sink unit has been installed in the Refs changing room
31st Oct 2014
The flooring has been laid down in the Ladies toilet
31st Oct 2014
The walls have been painted the chosen colours in the Meeting room
31st Oct 2014
The walls have been painted the chosen colours in the Meeting room
31st Oct 2014
The chairs have arrived for the Changing rooms