Memorial Pavilion – Building progress
Week 35. 20th – 24th Oct 2014
20th Oct 2014
The oak skirting has started to be installed around the Meeting room
20th Oct 2014
The oak skirting continues to be installed around the Main hall
20th Oct 2014
The oak skirting continues to be installed around the Main hall
20th Oct 2014
The vinyl flooring upstands have been installed in Changing room 1 to be ready for the flooring to be laid
20th Oct 2014
The vinyl flooring upstands have been installed in Changing room 1 to be ready for the flooring to be laid
20th Oct 2014
The vinyl flooring upstands have been installed in Changing room 1 to be ready for the flooring to be laid
20th Oct 2014
The vinyl flooring upstands have been installed in Changing room 1 to be ready for the flooring to be laid
20th Oct 2014
The flooring installer is preparing to install the upstands in the Kitchen. Notice that the water pipes have been installed
21st Oct 2014
The floor in Changing room 2 has been prepared for the vinyl to be laid down
21st Oct 2014
The floor in the Ladies toilet is being prepared for the vinyl to be laid down
22nd Oct 2014
The vinyl flooring upstands have been installed in the Refs room to be ready for the flooring to be laid. Note the pipework showing through the wall, this is for the sink unit in the room
22nd Oct 2014
The vinyl flooring upstands have been installed in the Ladies toilet to be ready for the flooring to be laid
22nd Oct 2014
The Kitchen water and waste pipes have been fitted ready for the kitchen units to be installed
22nd Oct 2014
Changing room 1 has had its second coat of wall paint and is now completed
22nd Oct 2014
The overflow car park has had some of its reinforcing netting laid down and secured
22nd Oct 2014
The overflow car park has had some of its reinforcing netting laid down and secured
23rd Oct 2014
The overflow car park has had the rest of its reinforcing netting laid down and secured
23rd Oct 2014
The overflow car park has had the rest of its reinforcing netting laid down and secured
23rd Oct 2014
The vinyl flooring upstands have been installed in Changing room 2 to be ready for the flooring to be laid
23rd Oct 2014
The two light fittings in the Lobby ceiling have been installed and connected