Memorial Pavilion – Building progress
Week 34. 13th – 17th Oct 2014
14th Oct 2014
The plant room access hatch has been fitted and the corridor ceiling is being painted
14th Oct 2014
The final section of Lobby wall has had the first (mist) coat of paint
14th Oct 2014
The area in front of the Main Entrance has been cleared and cleaned
14th Oct 2014
The oak skirting is being fixed in the Main hall and Meeting room before the flooring is laid
14th Oct 2014
The first fence posts have been fitted on the bridge
14th Oct 2014
The fittings are being installed in the Gents toilet
15th Oct 2014
The fittings are being installed in the Gents toilet
15th Oct 2014
The Plant room access hatch has been finished including the access ladder
15th Oct 2014
The first coat of the chosen colour has been put on the Kitchen walls
15th Oct 2014
The West wall canopy roofing has been completed
15th Oct 2014
The West wall canopy roofing has been completed
15th Oct 2014
Eight of the Bridge fence posts have been fitted into place
16th Oct 2014
All of the Bridge fence posts have now been fitted into place
16th Oct 2014
All of the Bridge fence posts have now been fitted into place
16th Oct 2014
The walls in Changing room 1 have been painted their chosen colour
16th Oct 2014
The walls in Changing room 1 have been painted their chosen colour
16th Oct 2014
The final coat of the chosen colour has been put on the Kitchen walls
16th Oct 2014
The final coat of the chosen colour has been put on the Kitchen walls
16th Oct 2014
The fittings are being installed in the Ladies toilet
16th Oct 2014
The fittings are being installed in the Ladies toilet
16th Oct 2014
The fittings are being installed in the Ladies toilet
16th Oct 2014
The walls in the Refs room have been painted in the chosen colour. The bare patch each side is the end of the shower wall and the whole shower area will be covered by waterproof plastic sheets
16th Oct 2014
The new fence is being fitted on the West end of the Bowls Green footpath. The extra bars on the bottom are to prevent rabbits from accessing the Bowls green. It now awaits the gate to be fitted
16th Oct 2014
The new fence is being fitted on the East end of the Bowls Green footpath. The extra bars on the bottom are to prevent rabbits from accessing the Bowls green. It now awaits the gate to be fitted