Memorial Pavilion – Building progress
Week 33. 6th – 10th Oct 2014
6th Oct 2014
The Disabled access ramp handrail has been installed and the brick paving finished off
6th Oct 2014
The Disabled access ramp handrail has been installed and the brick paving completed
7th Oct 2014
The Disabled parking area is being marked out
7th Oct 2014
The Disabled parking area is being marked out
7th Oct 2014
The pedestrian walkway across the bridge has been lined off and marked out with a “walking man”
7th Oct 2014
The pedestrian walkway across the bridge has been lined off and marked out with a “walking man”
7th Oct 2014
The Lobby walls have been painted with their first (mist) coat of paint
7th Oct 2014
The floor primer coat has been laid over the concrete floor in the Meeting Room ready for the latex leveling coat to be put down before the vinyl flooring is laid
7th Oct 2014
The floor primer coat has been laid over the concrete floor in the Main Hall ready for the latex leveling coat to be put down before the vinyl flooring is laid
8th Oct 2014
The floor primer coat has been laid over the concrete floor in Changing room 2 ready for the latex leveling coat to be put down before the vinyl flooring is laid
8th Oct 2014
The floor primer coat has been laid over the concrete floor in the Lobby ready for the latex leveling coat to be put down before the vinyl flooring is laid
8th Oct 2014
The door “furniture” is being applied to all doors. These are the Cleaners cupboard and Disabled toilet. Note the oak trim on the top of the door frames
8th Oct 2014
The door “furniture” is being applied to all doors. These are the Kitchen and the Disabled serving hatch.
8th Oct 2014
These plants have been generously donated and planted in the garden on the East wall
8th Oct 2014
This is a panoramic view of the near completed East wall
8th Oct 2014
This is a panoramic view of the near completed North wall
8th Oct 2014
This is a panoramic view of both the East and North walls taken from the bridge
8th Oct 2014
This is a panoramic view of both the South wall and the Machine hut taken from the bowls green
9th Oct 2014
The last room to have the floor primer laid is the Kitchen
9th Oct 2014
The lighting fittings have been installed in the Gents toilet
9th Oct 2014
The lighting fittings have been installed in Changing room 2
10th Oct 2014
The lighting fittings have been installed and are working in the Gents toilet and in nearly all other rooms
10th Oct 2014
The oak frame edge trims have been fitted on the Changing room 1 and Ref’s Changing room doors
10th Oct 2014
The oak frame edge trims have been fitted on the Cleaners cupboard and the Disabled toilet doors
10th Oct 2014
The Plant room access hatch doors are being fitted
10th Oct 2014
The West wall canopy roofing has been partially fitted as we have run out of the special screws. The last three panels will be fitted as soon as we get the screws from the manufacturer
10th Oct 2014
This is a panoramic view of the West wall
10th Oct 2014
The overflow car park ground has been rolled over to be ready for the plastic mesh to be laid and fixed down