Memorial Pavilion – Building progress
Week 32. 29th Sept – 3rd Oct 2014
29th Sept 2014
The oak fencing rails have begun to be installed with over half way completed
29th Sept 2014
The oak fencing rails installation has been completed
29th Sept 2014
The three car parking spaces at the bridge entrance area have had markers installed
29th Sept 2014
The seeded grass on the overflow car park has begun to grow after rain has started germination
29th Sept 2014
The new gate giving machine access to the bowls green has been erected with the concrete area laid and it will be rabbit proofed shortly
29th Sept 2014
Main entrance canopy ceiling is being lined with powder coated aluminium sheets to make it waterproof when rain is blown in under the canopy
29th Sept 2014
Main entrance canopy ceiling is being lined with powder coated aluminium sheets to make it waterproof when rain is blown in under the canopy
29th Sept 2014
The Disabled access ramp wall is waiting for the handrail to be manufactured and installed before the stone slabs can be mounted on top of the wall and the brick paving completed
29th Sept 2014
The surface of the bridge has been thoroughly cleaned and coated with a concrete sealant ready for the final tarmac surface to be laid
1st Oct 2014
The surface of the bridge has had a second coat of sealer put on with a sand coating applied, this aids the tarmac to grip the bridge surface
1st Oct 2014
The bridge fence posts have arrived back from the carpenter and await the top recess to be machined out
1st Oct 2014
The bridge fence posts have arrived back from the carpenter and the top recess has now been machined out
1st Oct 2014
The dado rail in changing room 1 is almost complete with the sockets installed
1st Oct 2014
The canopy ceiling on the Main Entrance is almost complete as it just waits for the edging strips to be installed around the window frame and in the apex of the roof, plus the light needs to be fitted
2nd Oct 2014
The tarmac contractors are sweeping up the excess bonding sand of the bridge concrete area to be ready for the tarmac surfacing to be laid
2nd Oct 2014
The tarmac surfacing has been laid and rolled flat and is being allowed to harden before any vehicles can cross the bridge
2nd Oct 2014
The tarmac surfacing has been laid and rolled flat and is being allowed to harden before any vehicles can cross the bridge
2nd Oct 2014
The road is being dug up to allow a duct to be installed to allow the telephone cable to be fed into the building
2nd Oct 2014
The Main hall and the Meeting room have been cleared of the contractors equipment and will be cleaned up ready for the latex coating to be laid on the floor to seal the concrete surface ready for the vinyl flooring to be laid
3rd Oct 2014
The galvanized handrail on the Disabled access ramp has been installed
3rd Oct 2014
The copper pipework for the underfloor heating has been connected to the manifolds
3rd Oct 2014
The domestic hot water storage tanks have been connected but are not at present working
3rd Oct 2014
The heat exchangers are being connected to the air source heat pumps and the copper pipes for the underfloor heating
3rd Oct 2014
The heat exchangers are connected as is all the copper pipes for the underfloor heating and it has been switched on (notice the two small green lights) to a very low heat setting to allow the floors to warm up very slowly so as not to crack the concrete