Memorial Pavilion – Building progress
Week 31. 22nd – 26th Sept 2014
22nd Sept 2014
The door into the Main Hall from the Lobby has been hung
22nd Sept 2014
The Main Hall large window has had the sill installed, protected by plastic and then the window sides plastered
22nd Sept 2014
The Main Hall South facing window has had the sill installed, protected by plastic and then the window sides plastered
22nd Sept 2014
The Changing room 2 window has had the sill installed, protected by plastic and then the window sides plastered
23rd Sept 2014
The door into Changing room 2 from the corridor has been hung
23rd Sept 2014
The door into Changing room 1 from the corridor has been hung
23rd Sept 2014
The door into Gents toilet from the corridor has been hung
23rd Sept 2014
The Dado rail which will have the electric sockets mounted in are being fixed to the walls in the Main Hall
23rd Sept 2014
The Dado rail which will have the electric sockets mounted in has been fixed to the walls in Changing room 1
23rd Sept 2014
The final surface layer of the entrance way and car park area has been laid
23rd Sept 2014
The final surface layer of the entrance way and car park area has been laid
24th Sept 2014
The car parking markers have been laid in the final surface layer
24th Sept 2014
The car parking markers have been laid in the grassed parking area
24th Sept 2014
The oak doors for the store room have been hung
24th Sept 2014
This section of dado rail in the Main Hall has been fitted with the electrical sockets and the final covering fitted
24th Sept 2014
This section of dado rail in the Main Hall has been fitted with the electrical sockets and the final covering fitted
25th Sept 2014
The Air Source heat pumps for the underfloor and domestic hot water heating are being installed
25th Sept 2014
The last walls of the Changing room 2 have been fully plastered
25th Sept 2014
The last unfinished Lobby ceiling and walls have been plastered
25th Sept 2014
The walls in the Main Hall are having their first (mist) coat of paint
26th Sept 2014
The walls around the entrance door have been plastered
26th Sept 2014
The last wall in the Kitchen has been plastered
26th Sept 2014
The Store room ceiling has been plastered
26th Sept 2014
The hot water storage tanks have been positioned in the Plant room awaiting all the connections to be made
26th Sept 2014
The Heat Exchangers have been mounted on the West wall of the Plant room and await their connections to be made
26th Sept 2014
The two bollards that allow access onto the overflow car park from the main car park have been fixed into place
26th Sept 2014
A gate has been installed next to the overflow car park to allow access by a Renovation machine for the Bowls Green Autumn restoration ready for the Winter
26th Sept 2014
This is a recent early morning view of the South side of the pavilion in the sunshine
26th Sept 2014
This is a long distance view from the top of Back Lane showing the overall outlook of the building in the landscape