Memorial Pavilion – Building progress
Week 30. 15th – 19th Sept 2014
15th Sept 2014
The paving slabs outside the main entrance door have been fixed into position
15th Sept 2014
The steps kerb stones holding the handrail in place have been fixed into position
15th Sept 2014
The steps kerb stones holding the handrail in place have been fixed into position
16th Sept 2014
The glazing is being installed into the window frames surrounding the main entrance door
16th Sept 2014
The Main Hall ceiling lights are being installed
16th Sept 2014
The oak internal door frames have arrived from the manufacturer
16th Sept 2014
The oak internal doors have also arrived from the manufacturer
16th Sept 2014
The last section of the overflow car park has been cleared and covered with top soil ready for the grass seed to be sown and the plastic support netting laid
16th Sept 2014
The bridge fencing posts support brackets have been fitted ready to receive the oak posts
17th Sept 2014
All the lights have been fitted into the ceiling of the Meeting room
17th Sept 2014
The window sills have arrived and are being cut to size and fitted, this one is in the meeting room
17th Sept 2014
The Oak door frames are being installed, this one is the Disabled toilet door frame
17th Sept 2014
The groundwork around the building is now being cleaned up and the penultimate surface is beginning to be laid and compacted down ready for the final surface shingle to be laid
17th Sept 2014
The overflow car park has had the grass seed spread over, raked in and more spread over and it now awaits the rain to germinate
17th Sept 2014
The Main car park has had the grass seed spread over, raked in and more spread over and it now awaits the rain to germinate
18th Sept 2014
The groundwork around the building has now been cleaned up and the penultimate surface has been laid and compacted down ready for the final surface shingle to be laid
18th Sept 2014
The white office container has been removed opening up the 4 car parking spaces
18th Sept 2014
The serving hatch into the Main Hall has had the electric roller shutter partially installed
18th Sept 2014
Changing room 1 ceiling and walls have had the first (mist) coat of paint applied
19th Sept 2014
The corridor ceiling and walls have had the first (mist) coat of paint applied
19th Sept 2014
The serving hatch into the Main Hall has had the electric roller shutter fully installed and tested
19th Sept 2014
The Oak door frames are being installed, the closest one is the Cleaners store and the picture also shows the Changing room 1 frame
19th Sept 2014
This is one of the oak doors that are being installed and this one is the Main Hall door into the Lobby
19th Sept 2014
The river/roadside oak fencing is being installed. Note the metal brackets poking out of each post, these are to secure the oak rails between the posts
19th Sept 2014
The last section of knee fencing has been installed beside the access path from the parking area onto the playing field