Memorial Pavilion – Building progress
Week 3 – 10th – 14th March
10th Mar 2014
Sign erected on fence to show Lottery involvement
11th Mar 2014
Preparation of the reinforcing ready for the concrete pour in the next batch of foundations
11th Mar 2014
Placing the concrete blocks into position ready for the first laying of lower wall up to the damp proof course at floor level
12th Mar 2014
The second batch of foundations with reinforcing laid ready for the concrete
12th Mar 2014
The second batch of foundations with concrete laid in and hardened
13th Mar 2014
The finished foundations with all concrete laid
13th Mar 2014
Laying the concrete blocks on the West wall up to the damp proof course
14th Mar 2014
South wall showing the concrete blocks laid. The gaps in the wall are for the steel support columns
14th Mar 2014
West wall showing the concrete blocks laid. The gaps in the wall are for the drain pipes from the showers, changing rooms and toilets
14th Mar 2014
North wall showing the foundations ready for the steel support columns to be erected and the concrete blocks to be laid