Memorial Pavilion – Building progress
Week 29. 8th – 12th Sept 2014
8th Sept 2014
The Disabled access ramp brick paving progresses well after a delay in laying it down due to other work commitments in the building
8th Sept 2014
Progress on the paving slabs on the path from the entrance steps to the North West corner
9th Sept 2014
Further progress on the paving slabs on the path from the entrance steps to the North West corner. The last small slab cannot be put in due to the steps handrail needing to be fixed into the hole first
9th Sept 2014
The Disabled access ramp brick paving is almost complete. The bricks left out of holes next to the ramp wall are to allow access for the handrail to be fixed into position
9th Sept 2014
The underfloor heating pipes emanating from the manifold in the Lobby have had additional insulation fitted onto the hot water flow pipes to prevent the floor screed from getting too hot due to so many pipes being close together
9th Sept 2014
The underfloor heating pipes emanating from the manifold in the Store room have had additional insulation fitted onto the hot water flow pipes to prevent the floor screed from getting too hot due to so many pipes being close together
9th Sept 2014
The cement floor screed has been laid in Changing room 2
9th Sept 2014
The cement floor screed has been laid in the Ladies toilet room
9th Sept 2014
The cement floor screed is being laid in the Main Hall
10th Sept 2014
The cement floor screed has been laid in the Main Hall
10th Sept 2014
The cement floor screed has been laid in the Meeting room
10th Sept 2014
The special Disabled paving slabs in front of the Disabled access ramp have been grouted
10th Sept 2014
The North West corner paving slabs have been curved to allow cars to turn the corner safely
10th Sept 2014
The special Disabled paving slabs have been laid and grouted in front of the steps to the main entrance
10th Sept 2014
Two (Rodney and Brian) of the team of weed removers of the overflow car park in front of the large pile of weeds
10th Sept 2014
The overflow car park now clear of weeds
11th Sept 2014
The floor screed in the Kitchen has been finished
11th Sept 2014
The floor screed in the Corridor has been finished
11th Sept 2014
The main entrance steps handrails have arrived from the manufacturer
12th Sept 2014
The main entrance steps handrails have been installed
12th Sept 2014
The Store room has had the floor screed laid
12th Sept 2014
The second Mat well has been installed in the corridor
12th Sept 2014
The whole Lobby area including the Disabled toilet, Ref’s Changing room, Cleaners store and Changing room 1 have had their floor screeds laid, note the Mat well in front of the entrance door
12th Sept 2014
The roller shutter has been installed in the Main Hall and will be used to separate the Main Hall from the Meeting room, but it can be raised to make one large room for big functions
12th Sept 2014
The Outside store has had a roller shutter installed for security
12th Sept 2014
The Outside store has had a roller shutter installed for security
12th Sept 2014
The slabs are being laid on the top of the stairs in front of the main entrance door
12th Sept 2014
This path has been laid to allow comfortable access from the parking area to the playing field and the Children’s Play area
12th Sept 2014
The Overflow car park ground has been disc cut, harrowed and ring rolled to be ready for the grass seed and the support netting to be installed
12th Sept 2014
The Overflow car park ground has been disc cut, harrowed and ring rolled to be ready for the grass seed and the support netting to be installed