Memorial Pavilion – Building progress
Week 28. 1st – 5th Sept 2014
1st Sept 2014
The Kitchen ceiling and one wall has been plastered, note the underfloor insulation is also being laid
1st Sept 2014
The Main Hall West wall has been plastered and the floor is being cleaned ready for the underfloor insulation to be laid down
1st Sept 2014
The Main Hall East wall has been plastered
1st Sept 2014
The Main Hall North wall has been plastered
1st Sept 2014
The underfloor insulation has been laid in the corridor, toilets and changing room 2
1st Sept 2014
The Meeting Room has had the underfloor insulation laid down
1st Sept 2014
The Plant Room has had the walls and ceiling plastered. The square openings give access to the inner roof spaces and they will have fireproof doors fitted
1st Sept 2014
The Plant Room walls and ceiling have been plastered. The electrical items on the end wall are the units for the Solar panel generated electricity
2nd Sept 2014
The underfloor insulation has been laid down in the Main Hall
2nd Sept 2014
The wall in the Main Hall around the serving hatch has been plastered. Note also the lobby wall through the doorway has also been plastered and the underfloor insulation has been laid
2nd Sept 2014
The East wall of the meeting room has been plastered
2nd Sept 2014
The lobby wall with the second serving hatch in has also been plastered. The long gaps in the underfloor insulation are for the water pipes to the manifold for the underfloor heating on the right and the hot/cold water supply to the kitchen on the left. The insulation will then be laid down once the pipes are in situ
2nd Sept 2014
Inside the Kitchen the wall with the second serving hatch in has also been plastered. Note the insulated pipe in the middle of the wall, this is the mains water feed for the boiler to be used for making tea and coffee
3rd Sept 2014
The Refs room shower area has had the walls rendered with mortar to be ready for the shower wall coverings
3rd Sept 2014
The Main Entrance steps have been built and covered over with plastic and wood to protect them from getting dirty or damaged. Note also the steps on the righthand side of the entrance
3rd Sept 2014
The Main Entrance steps have had a flint wall built on each end. Note how thick the step slabs are!
4th Sept 2014
The ‘Landing’ slabs have been laid, note the rippled slabs, these are for partially sighted people to know by feeling through their feet where they are in relation to the steps
4th Sept 2014
The ‘Landing’ slabs have been laid, note the rippled slabs, these are for partially sighted people to know by feeling through their feet where they are in relation to the steps
4th Sept 2014
The South East wall in the Main Hall has been plastered
4th Sept 2014
The Main Hall doorway wall has been plastered
4th Sept 2014
The Meeting Room wall in the Lobby has been plastered
4th Sept 2014
This photo shows the route taken by the underfloor heating main flow and return pipes to the second manifold in the Store room. This will supply the heating to the Main Hall, Meeting room and Store room
5th Sept 2014
Underfloor heating pipes laid down in the Kitchen
5th Sept 2014
Underfloor heating pipes laid down in the Disabled toilet
5th Sept 2014
Underfloor heating pipes laid down in the corridor entrance to Changing room 1. This shows the first manifold
5th Sept 2014
Underfloor heating pipes laid down in the Gents toilet
5th Sept 2014
Underfloor heating pipes laid down in the Ladies toilet
5th Sept 2014
Underfloor heating pipes laid down in the Changing room 2. This is the same in Changing room 1
5th Sept 2014
Underfloor heating pipes laid down in the Changing room 2 shower room. This is the same in the Changing room 1 Shower room
5th Sept 2014
Underfloor heating pipes laid down in the corridor
5th Sept 2014
Underfloor heating pipes laid down in the Lobby area
5th Sept 2014
Underfloor heating pipes laid down in the Ref’s room
5th Sept 2014
Underfloor heating pipes laid down in the Meeting room
5th Sept 2014
Underfloor heating pipes laid down in the Meeting room and Main Hall
5th Sept 2014
Underfloor heating pipes laid down in the Store room and Main Hall. This shows the second manifold
5th Sept 2014
Underfloor heating pipes laid down in the Main Hall and Meeting room
5th Sept 2014
The Main Hall Kitchen wall has been plastered
5th Sept 2014
The brick paving is being laid on the disabled access ramp
5th Sept 2014
The paving slabs for the path from the main entrance steps towards the West corner are being laid
5th Sept 2014
The main entrance window frame and door have been fitted into place. The ribbed plastic in the side windows is just a temporary measure
5th Sept 2014
This door, which overlooks the Bowls green is the fire exit from the Main Hall
5th Sept 2014
This door, which overlooks the Bowls green is the fire exit from the Meeting room