Memorial Pavilion – Building progress
Week 27. 26th – 29th Aug 2014
26th Aug 2014
The disabled ramp wall has been completed to brick paving level. Note the flints
26th Aug 2014
The disabled ramp has been infilled and tamped down ready for the brick paving to be laid
26th Aug 2014
The corridor wall has been plastered and has not quite dried out yet
26th Aug 2014
The Changing room 1 has most of its walls plastered
26th Aug 2014
The Changing room 2 has half its walls plastered
26th Aug 2014
All walls in the Gents toilet have been plastered
26th Aug 2014
All walls in the Ladies toilet have been plastered
26th Aug 2014
Half of the walls in the meeting room have been plastered
27th Aug 2014
All the walls in the kitchen have been plasterboarded
27th Aug 2014
All the walls in the kitchen have been plasterboarded
28th Aug 2014
The first room to have the underfloor heating insulation installed is Changing Room 1
28th Aug 2014
The canopy facing the bowls green has had the steel roof fitted on
28th Aug 2014
The galvanized brackets for the bridge fence posts and the rails have been delivered from the manufacturer
28th Aug 2014
A fence post bracket has been fitted into the ground next to the bridge
28th Aug 2014
This is a view of the building from across the bowls green, note the canopy steel roof has been fitted
28th Aug 2014
The kitchen ceiling has been plastered and it is slowly drying out
28th Aug 2014
Underfloor insulation has been laid down in the Gents toilet room ready for the underfloor heating pipes to be installed
28th Aug 2014
Underfloor insulation has been laid down in Changing room 1 ready for the underfloor heating pipes to be installed
28th Aug 2014
Underfloor insulation has been laid down in Shower room 1 ready for the underfloor heating pipes to be installed