Memorial Pavilion – Building progress
Week 26. 18th – 22nd Aug 2014
18th Aug 2014
The knee fence post holders have been placed in the ground ready for the posts and rails to be fitted around the overflow car park access point
18th Aug 2014
The disabled parking area has had a drain put in close to the bridge entrance to allow rainwater to drain away
18th Aug 2014
The disabled parking area brick paving continues to expand and the bicycle racks are now in place. The blue covered packets contain the underfloor heating insulation
19th Aug 2014
The disabled parking area brick paving continues to expand and the bicycle racks are now in place. The blue covered packets contain the underfloor heating insulation
19th Aug 2014
The lobby walls continue to be covered in plasterboard to be ready for a coat of plaster
19th Aug 2014
The curved corridor wall has been screeded with cement to be ready for a coat of plaster
20th Aug 2014
The disabled parking area brick paving continues to expand and the bicycle racks are now fully bricked in
20th Aug 2014
The Knee fence each side of the overflow car park entrance has been completed
20th Aug 2014
The Knee fence along the car parking area next to the playing field has been erected
20th Aug 2014
The plaster boarding of the meeting room walls has been completed ready for a coat of plaster
20th Aug 2014
The plaster boarding of the kitchen walls has started
21st Aug 2014
The Knee fence on the corner car park area has been completed
21st Aug 2014
The Knee fence on the corner car park area has been completed
21st Aug 2014
The disabled parking area brick paving continues to expand and is near completion
21st Aug 2014
The shower rooms have had a cement screed laid on the walls
21st Aug 2014
The post holders have been positioned next to the parking area brick paving ready for the oak fencing to be erected
21st Aug 2014
The wall for the disabled access ramp is being constructed ready for the brick paving to be laid