Memorial Pavilion – Building progress
Week 23. 28th July – 1st Aug 2014
28th July 2014
The outside store construction is now completed and the brick and flints are being washed
28th July 2014
The spectators canopy on the West wall has been positioned ready to be fixed in place
28th July 2014
The plasterboard has been placed in the main hall ready to be fixed to the walls after the scaffolding has been removed
29th July 2014
The ceiling in the lobby has had its first (mist) coat of paint to seal the plaster
29th July 2014
The ceiling in the main hall has had its first (mist) coat of paint to seal the plaster
29th July 2014
This view shows the North side of the building without any scaffolding
29th July 2014
This view shows the South side of the building without any scaffolding and the solar panels on the roof
30th July 2014
The South wall without any scaffolding and the canopy supports fixed in place
30th July 2014
The West wall without any scaffolding and the canopy supports fixed in place
30th July 2014
The Meeting room without scaffolding looking towards the Bowls Green
30th July 2014
The outside store with the scaffolding removed is now complete
30th July 2014
The outside store with the scaffolding removed is now complete
31st July 2014
The shrub garden on the East wall has the dirt laid in
31st July 2014
The first two window frames installed in the Kitchen and Lobby window openings
31st July 2014
The paving slabs being laid on the South wall path in front of the Bowls Green. Note the window frames waiting to be installed
31st July 2014
The paving slabs being laid on the West wall path under the canopy
1st Aug 2014
Over half of the paving slabs laid and the joints being grouted on the South wall path
1st Aug 2014
The paving slabs laid on the West wall path under the canopy
1st Aug 2014
A panoramic view of the South wall and the outside store from the bowls green