Memorial Pavilion – Building progress
Week 22. 21st – 25th July 2014
21st July 2014
The roof tiling is now complete and it is fully watertight! The next job, after the scaffolding is down, is to fit the gutters and downpipes
21st July 2014
Progress is speeding up to complete the outside store walls ready for the roof tiling to be installed
21st July 2014
The South and West side spectator canopies supports have arrived from the manufacturers and will be erected once the scaffolding is removed
22nd July 2014
The black plastic covered boxes on the East wall have been uncovered to reveal the name and construction date of the building
22nd July 2014
This is a view across the playing field from the West
22nd July 2014
The walls are being cleaned with a very mild acid solution and then pressure washed down
22nd July 2014
The scaffolding around the canopy for the lobby has been partially taken down to reveal the oak fascias
22nd July 2014
The wiring is being installed very neatly by the electricians
23rd July 2014
The lobby ceiling has had the plasterboard fitted and awaits the plaster skim
23rd July 2014
The galvanized guttering and downpipes have been installed on the North wall
23rd July 2014
The main hall ceiling is being covered with plaster
24th July 2014
The galvanized guttering and downpipes have been installed on the South wall
24th July 2014
The East wall has been fully washed down and the guttering erected. It now awaits the windows
24th July 2014
The roof tiling has been finished on the outside store. The guttering and downpipes are to be installed and the flashing to be fitted down onto the tiles
25th July 2014
The scaffolding has been taken down half way along the South wall. The other half is staying to allow the solar panels to be installed
25th July 2014
The scaffolding has been taken down from the North wall and the wall is still being cleaned