Memorial Pavilion – Building progress
Week 20. 7th – 11th July 2014
7th July 2014
The ceiling insulation has arrived and is being prepared to be installed in the main hall
7th July 2014
The outside store walls are going up and the back wall has reached the lower height of the sloping roof
8th July 2014
The outside store walls continue to go up and the back wall is now ready for the flintwork
8th July 2014
The roof tiles are now being placed out all over the South facing roof ready to be fixed into position
9th July 2014
The roof tiles are being fixed into position on the South facing roof
9th July 2014
The outside store wall facing the road is having the flintwork done
9th July 2014
The outside store wall facing the bowls green is having the flintwork done
10th July 2014
The flintwork on the outside store walls has been completed up to scaffolding height
10th July 2014
The roof tiles are now being fixed into position on the East end of the North facing roof
11th July 2014
The roof tiles are now being fixed into position on the West end of the North facing roof
11th July 2014
The scaffolding has been erected around the outside store hut ready to complete the walls and roof
11th July 2014
The main hall ceiling is being fitted with a double layer of insulation. The square cutouts are for the light fittings
11th July 2014
The wiring in the kitchen has been installed to allow the ceiling to be fitted