Memorial Pavilion – Building progress
Week 19. 30th June – 4th July 2014
30th June 2014
The West wall brick and flintwork is now complete
30th June 2014
The East wall flintwork is still progressing upwards with the final three layers of brick to be laid on top
30th June 2014
The size of the kitchen is being increased by moving the internal store room wall back by 1 metre The wall has been pulled down and awaits re-building in the new position
30th June 2014
The digging of the foundation for the store hut has been started
1st July 2014
The foundations for the store hut have been dug ready for the concrete
1st July 2014
The concrete being poured into the foundation trench
1st July 2014
The East wall brick and flintwork has been completed
2nd July 2014
The two Velux rooflights have been installed in the lobby roof
2nd July 2014
The roofers have started putting on the felt ready for the roof tiles
3rd July 2014
The whole roof has now been covered with roofing felt so making the building more watertight
3rd July 2014
The whole roof has now been covered with roofing felt so making the building more watertight
3rd July 2014
The whole roof has now been covered with roofing felt so making the building more watertight
3rd July 2014
The block and brickwork for the store hut foundations are being laid to be ready for the concrete floor to be laid
4th July 2014
The South facing roof dorma over the meeting room is being faced with oak
4th July 2014
The kitchen wall is being built up in the new position 1 metre further back into the store room
4th July 2014
The concrete floor for the store hut is being laid