Memorial Pavilion – Building progress
Week 18: 23rd – 27th June 2014
23rd June 2014
Laying flint on the West wall
23rd June 2014
West wall flintwork being done. The triangle of brickwork is where the two Air Source Heatpumps will be fixed
24th June 2014
West wall progressing upwards but now requires the scaffolding walkway to be lifted to allow completion of gable end
24th June 2014
The lobby canopy’s oak fascia and barge boards have been fixed into place
25th June 2014
The west wall scaffolding has been raised to allow completion of the gable end
25th June 2014
The South side roof rafters have all been laid in place
25th June 2014
The East wall is growing upwards
26th June 2014
The scaffolding has been raised up to allow completion of the East wall gable end
26th June 2014
The framework for the Velux rooflight has been made in the lobby roof
26th June 2014
The South side roof dorma has been constructed to be ready for the roof tiles
26th June 2014
The West wall is nearing completion with the last row of bricks being laid. Note the breather feature at the ridge point which allows fresh air into the roof space
26th June 2014
Further progress on the East wall with the blocks in place up to the ridge point