Memorial Pavilion – Building progress
Week 12. 12th – 16th May
12th May 2014
View of main hall and the meeting room showing the two pillars erected to support the roller shutter that seperates the two rooms
12th May 2014
View showing the meeting room window and door aperture and one roller shutter pillar
13th May 2014
East wall with the flints in position under main window with scaffolding inside the room to allow access to build up the block walls
13th May 2014
Meeting room showing the scaffolding in position ready for the interior block walls to be built up to allow the steelworks to be erected
13th May 2014
Corridor showing the lintels being fixed in position ready for the interior walls to be built up to the plant room floor level
14th May 2014
Main hall wall showing the steel beam across the roller shutter opening ready for the block-work to be laid on top
14th May 2014
Kitchen showing the lintel over the main hall serving hatch in position and the block-work being laid over
15th May 2014
The lobby showing the steel roof support beam connected into the meeting room block wall
15th May 2014
The floor joists for the Plant Room have been laid
15th May 2014
The corridor ceiling access hatch opening to the plant room has been constructed
16th May 2014
The bricks have arrived and are being unloaded ready for the walls to be built next week
16th May 2014
The two support walls for the rest of the roof steelworks have been surveyed to obtain the correct height of the block-work for the laying of the pad-stones
16th May 2014
The pad-stones being laid to allow them to harden before the rest of the roof steelworks is completely erected next week