Memorial Pavilion – Building progress
Week 1. 24th – 28th Feb
23rd Feb 2014
Site before the start of work
24th Feb 2014
The hedgehog base and bench seat have been moved as they were in the path of the site security fence
25th Feb 2014
The new site security fence erected and showing some of the car park top soil removed and stone to be laid in as this becomes the position for the site accommodation huts
25th Feb 2014
The hedge along the bowls green has started to be removed
25th Feb 2014
The first layer of hardcore being laid on the car park area
26th Feb 2014
The bowls green hedge has now completely gone and protection fencing put up so the bowls team can still carry on playing on the green this season
26th Feb 2014
Tons of soil being moved from the site
27th Feb 2014
Part of the planning regulations requires a test wall be constructed so that the Planning Dept can see what the building walls will look like and to see it meets their approval for the conservation area